Project Type: Two Storey Residential Structure
Project Cost: P3,200,000.00 (Three Million Two Hundred Thousand Pesos)
Scope of Works
I. General Requirements
a. Mobilization, Materials Handling
a. Site Clearing
b. Temporary Facilities
c. Demolition
d. Excavation
e. Demobilization
f. Hauling
II. Concrete Works
a. Foundation (Excavation, Pouring of concrete, steel fabrications) b. Footing (Excavation, pouring of concrete, steel fabrications)
c. Wall Footing (Excavation, pouring of concrete, steel fabrications)
d. Tie Beams (Excavation, formworks, pouring of concrete, steel fabrications)
e. Columns (Formworks, scaffolding, pouring of concrete, steel fabrications)
f. Beams (Formworks, scaffolding, pouring of concrete, steel fabrications)
g. Roof Beams (Formworks, scaffolding, pouring of concrete, steel fabrications)
h. Concrete Slab Works (Formworks, scaffolding, poring of concrete, steel fabrications)
i. Canopies
j. Counter Top
k. Fencing are excluded
l. Outdoor slab works are excluded
III. Masonry Works
a. CHB Laying and CHB reinforcements
b. Brick Works (Limited to conservative finish)
c. Stone Works (Limited to conservative finish)
IV. Roofing and Tinsmitry
a. Truss work
b. Roofing Installations (.40mm thick Rib Type Roofing)
c. Gutter Installations (Colored S-gutter)
V. Finishing Works
a. Plastering
b. Ceiling Works ( Limited to conservative finish)
c. Tile Works
-Ground Floor common areas (Granite Tiles .60x.60m)
-Toilet and Bath (.20x.30 and .20x.20m ceramic tiles)
-Counter Top (Granite Tiles .60x.60m)
-Laminated Flooring for al l rooms
-Second floor common areas (Granite Tiles .60x.60m)
d. Painting Works (Interior and exterior painting)
e. Carpentry works , Cabinets(Limited to conservative finish, surface prepared but not painted)
f. Doors (Panel and flush doors, aluminum framed sliding doors, hardware)
g. Windows (Aluminum framed sliding, awning and fixed windows)
h. Landscaping are excluded
XV. Electrical Works
a. Electrical rough-ins, power and lighting lines
b. Main entrance, Panel board
c. Lighting and power fixtures are excluded (switches, outlets, drop lights, pin lights, other fixtures)
XVI. Sanitary Works
a. Septic Vault
b. Sanitary lines
c. Installation of fixtures (Bath tub,Shower and heater fixtures are excluded)
d. Storm drain
XVII. Plumbing Works
a. Cold Water line installations
b. Deep well, pump installations (Excluded)
XVIII. Metal Works (Stairs,Veranda Steel Railings) (Gate, Fence,Window Grilles, and other items not included in the items are excluded)