Proposed One Storey House and Bill of Materials and Estimates

Project Title: Proposed One Storey Three (3) Bedroom Residence

Bill of Materials and Estimates

I.    Concrete and Masonry      – 398,502.50

40 kgs Portland Cement
Washed sand
5” chb
4” chb
8 mm bars
9 mm bars
12 mm bars
GA #16 tie wire
3/4 crushed gravel

II.    Carpentry – 38,775.00

1/4” x 1/4” thk ordinary plywood
1/4” x 1/4” marine plywood
1” x 2” x 1 1/2″ x 12 coco lumber
2” x 2” x 12” lumber
2” x3” x 12” lumber
Assorted nails

III.    Steel Trusses – 45,485.00

L bar 3/16×1 1/2x 1 ½”
C-Purlins 2x3x1.20
C-Purlins 2x6x1.0
1/8 x 1 ½ Flat Bar
Welding Rod
Metal Primer
Paint Thinner
Paint Brush
Hacksaw Blade

IV.    Roofing Materials – 61,772.50

Longspan sheet roofing
Ridge roll
Tekscrew
Type-S Sealant
Silicon Sealant
Touch-up paint
Blindrivets
Color Gutter 24”

V.    Doors – 20,792.00

Main panel door
Panel door .80 x 2.10
3  1/2×3 1/2 hinges
PVC Flush door
Door knobs

VI.    Windows – 45,300.00

1.40 x 1.20 aluminum sliding window
0.50 x 0.60 aluminum sliding window

VII.    Plumbing Rough-in – 15,340.00

Water closets
Stainless Kitchen Sink
4” x 4” Floor Strainer
12 mm water faucet
Water line
PVC assorted fixtures

VIII.    Tile Works – 57,345.00

8” x 10” ceramic wall tiles
8” x 8” ceramic floor tiles
40×40 Ceramic Floor Tile
Tile Grouth
Portland Cement

IX.    Electrical Works – 16,720.00

3” dia. Porcelain receptacle
60 watts energy savers
Single switch
Two gang
Three gang
2” x 4” utility box
4” x 4” junction box
Panel box
Electrical Wires
Safety switch
Moldflex PVC Pipe

X.    Painting Works – 53,750.00

Latex flat
Gloss latex flat wall
Enamel
Flat wall enamel
Metal Primer
Acri-color
Conc. Neutralizer
Paint thinner
Sandpaper
Q.D.E.

XI.    Embankment/Earthfill  – 45,000.00

TOTAL – 798,782.00

Summary

A.    Material Cost – Php 798,782.00
B.    Labor Cost – Php 399,391.00
Total Probable Project Cost – Php 1,198,173.00

Prepared by:

Architect Ted M. Co